Slope Stabilisation

Bana Gindarja Creek, Edmonton

Key Capabilities: Slope Stabilisation including soil nailing and shotcrete works. Detailed Earthworks & Pavement Construction
Location: Edmonton, North Queensland
Client: Department of Transport and Main Roads
Duration: June 2024 – May 2025

About the Project:

The Bana Gindarja Creek Stabilisation works formed the final link between the Cairns Southern Access Cycleway and the Edmonton to Gordonvale Stage 4 project. The works involved stabilising Bana Gindarja Creek, an area of significant cultural heritage, and constructing a high‑speed cycleway connecting Gordonvale to Cairns.

Project Scope

Project works included the construction of a high speed cycleway involving.

  • Soil nailing for batter stabilisation
  • Rock revetments
  • Storm water drainage
  • Shotcreting and Pavement works

Challenges

  • Our team successfully delivered works within the sensitive footprint of Bana Gindarja Creek and a National Park, both areas recognised for their significant cultural heritage.
  • Operating within the Queensland Rail Corridor, we partnered closely with Indigenous groups and Queensland Rail to ensure respectful, collaborative, and
    day-to-day project delivery.
  • This approach reflects our commitment to cultural heritage, stakeholder engagement, and operational excellence in civil construction.

Achievements:

  • Our Team delivered the project safely and efficiently within the live Queensland Rail Operations Corridor
  • The scope involved the precision installation of soil nails to tight tolerances, all in close proximity to sensitive assets and critical infrastructure
  • Navigating steep terrain, limited site access, and the nearby creek demanded a thoroughly planned construction program and innovative solutions to maintain safety and minimise impact
  • This achievement was possible through collaboration, with our team working hand in hand with all stakeholders

 