Slope Remediation
D'Aguilar Highway
Location: D’Aguilar Highway, South East Queensland
Client: RoadTek – North Coast
Start Date: Jan 2024
End Date: July 2024
Value: $1.9m
About the Project:
Major remediation works were required for a failed shotcrete batter that was constructed in 2011/2012 on D’Aguilar Highway approximately 11.4 km east of Blackbutt township. This project included the staged removal of the existing shotcrete batter and installation of soil nails and new shotcrete batter. Due to the in situ material, the removal of the damaged shotcrete and descaling of the existing batter proved to be very challenging. Removal and replacement of the toe slab was apart of the original scope.
Project Highlights
- Traffic Management
- Removal of damaged shotcrete and slab
- Staged descaling of existing material
- Soil nail including testing
- Staged Reinforcement and Concreting
Key Challenges and Solutions
- HEH Civil worked collaboratively with Roadtek and DTMR throughout construction to manage the implementation of design changes, issued post contract award. Good communications and proactive planning ensured seamless integration of design changes without impacting delivery of the works to project programme.
- The staging of the removal of existing shotcrete caused some challenges issues but the experienced onsite project team were able to find solutions that benefit ed all stakeholders.
Achievements
- Project was on track to be delivered on time, safely and within budget.
- HEH Civil has maintained a good working relationship and communication with Principal Contractor and all stakeholders involved in the project to ensure safe delivery of the works with minimal impacts to the public.
Community Outcomes
- A proactive approach to stakeholder management practices ensured all stakeholder considerations and expectations were understood, consistent communications were maintained with the local community and all project objectives were achieved.